Singapore Mass Rapid Transit
SystemMott MacDonald was awarded the design contracts for
the first two of the four sections of the Singapore Mass Rapid
Transit System which required the railway to be carried on elevated
structures. The length of viaducts on Mott MacDonald’s design
contracts totalled 10.3km.
The elevated route passes through densely built-up areas and
the viaduct is typically located either in the median of a dual
carriageway or beside a road.
Precast post-tensioned concrete box girder beams were considered to
be the most appropriate of a number of structural forms considered
for the viaduct deck, in order to meet the very tight construction
programme. This allowed the beams to be manufactured under factory
conditions at a number of precasting yards along the route. They
were then transported along the ready constructed viaduct and
launched into position by specially designed gantries without
disruption to the adjacent road traffic. The MRT standard viaduct
carried two ballasted track a minimum of 4.3m apart, each track
being carried on a separate beam. The required use of ballasted
track permitted the use of simply supported spans without adversely
affecting the track design. The precast beams, weighing up to 180
tonnes, are supported at their ends on in-situ concrete crossheads
topping single piers on piled foundations. Two standard beam types
were designed, approximately 17m and 23m in length. By adjusting
the length of the crossheads it was thus possible to accommodate
any span between 20m and 30m using the standard units.
Considerable attention was given both to the visual impact of the
viaduct as a whole and to the detail of the surface finishes of the
piers and the deck. A curved side profile to the box girder was
adopted and the bottom corners of the girder were rounded to soften
its appearance. For similar reasons the piers are circular in cross
section. At a number of locations, where crossings of rivers or
major road junctions were required, the standard viaduct design was
inappropriate and a variety of long span structures were designed
with spans of up to 55m. These were designed to be an extension of
the viaduct form, so that the profile of the typical deck was
retained, haunches being introduced where required to provide
additional strength.
The design contracts required detailed design drawings and full
contract documentation to be prepared in a very short time, and
considerable use was made of computer aided design and detailing. A
suite of programs was used to produce setting out data, the
alignment design, contract drawings and bills of quantities.
Design Contract 102D comprised 3.3km of twin and triple track
viaduct with elevated stations at Ang Mo Kio and Yi Chu Chang.
Design contract 200D comprised 7km of twin track viaduct
incorporating nine in-situ prestressed long span structures
crossing road, railway and river, and an in-situ four span turnout
to the depot. Elevated stations were at Redhill, Queenstown,
Commonwealth, Buona Vista and Clementi.
These sections of the system were opened in 1987.